The FIDIC Red Book is one of the most widely used standard forms of construction contract. Published by the International Federation of Consulting Engineers (FIDIC), it is generally intended for building and engineering works designed by the Employer.
The FIDIC Red Book 1999 was widely adopted for international construction projects. The FIDIC Red Book 2017, its second edition, introduced more detailed procedures for contract administration, claims, project programmes, the Engineer’s determinations, and dispute resolution.
Understanding the differences between these editions is important for employers, contractors, civil engineers, quantity surveyors, project managers, and contract administrators.
1. Overview of FIDIC Red Book 1999 and 2017
Both editions provide a framework for defining the parties’ obligations, managing construction work, assessing claims, and resolving disputes. The 2017 edition retains the basic structure and many underlying principles of the 1999 edition but makes several procedures more detailed and prescriptive.
The main objective of these changes is to improve communication, promote timely decision-making, and reduce uncertainty during project execution. However, the practical effect of any provision depends on the contract’s Particular Conditions and applicable law.
2. FIDIC Red Book 1999 vs 2017: Complete Comparison Table
| Area | FIDIC Red Book 1999 | FIDIC Red Book 2017 |
|---|---|---|
| Edition | First Edition, 1999 | Second Edition, 2017 |
| Main clause structure | 20 main clauses | 21 main clauses |
| Engineer’s role | Primarily addressed under Sub-Clause 3.1, with determinations under 3.5 | More detailed provisions under Clause 3; agreement and determination procedure under 3.7 |
| Engineer’s determinations | Sub-Clause 3.5 | Sub-Clause 3.7, with a more detailed procedure and express neutrality requirements |
| Programme | Sub-Clause 8.3 | Sub-Clause 8.3, with more detailed programme requirements |
| Advance warning | Advance warning obligations are included in Sub-Clause 8.3 | Separate advance-warning provision under Sub-Clause 8.4 |
| Extension of Time (EOT) | Sub-Clause 8.4 | Sub-Clause 8.5 |
| Delays caused by authorities | Sub-Clause 8.5 | Sub-Clause 8.6 |
| Rate of progress | Sub-Clause 8.6 | Sub-Clause 8.7 |
| Delay damages | Sub-Clause 8.7 | Sub-Clause 8.8 |
| Contractor’s claims | Sub-Clause 20.1 | Sub-Clause 20.2 |
| Employer’s claims | Sub-Clause 2.5 | Common claims procedure under Clause 20, including Sub-Clause 20.2 |
| Notice of Claim | Contractor generally gives notice within 28 days of awareness, or when it should have become aware, of the event | The 28-day period generally remains, with a more detailed procedure for late notices |
| Fully detailed claim | Generally due within 42 days after awareness, subject to the contract | Generally due within 84 days after awareness, subject to the contract |
| Contemporary records | Relevant record-keeping requirements apply | More explicit requirements within the detailed claims procedure |
| Continuing claims | Addressed under Sub-Clause 20.1 | More detailed procedure under Sub-Clause 20.2 |
| Claims and disputes | Combined under Clause 20 | Claims under Clause 20; disputes and arbitration under Clause 21 |
| Dispute board | Dispute Adjudication Board (DAB) under Clause 20 | Dispute Avoidance/Adjudication Board (DAAB) under Clause 21 |
| Contract administration | Procedures are comparatively less detailed in several areas | More prescriptive procedures, notices, programme requirements, and timelines |
The table summarises the standard editions. Always check the signed contract, Particular Conditions, and applicable amendments before relying on a clause number or deadline. <Cite refs={[“turn108442search0″,”turn108442search4″,”turn108442search22″,”turn108442search24”]}/>
3. Key Differences Explained
A. Engineer’s Role and Determinations
Under the 1999 edition, the Engineer’s agreement and determination procedure is addressed in Sub-Clause 3.5.
In the 2017 edition, Sub-Clause 3.7 introduces a more detailed procedure. The Engineer is required to consult with the parties to try to reach agreement and, if agreement is not reached, proceed to a determination in accordance with the contract. The 2017 wording also expressly addresses the Engineer’s neutrality when carrying out these functions.
Practical implication: Contract administrators should carefully record consultations, submissions, and determinations. Parties must also monitor the applicable time limits for challenging a determination through a Notice of Dissatisfaction.
B. Extension of Time and Delay Management
In the 1999 edition, Extension of Time for Completion is covered by Sub-Clause 8.4. In the 2017 edition, it is covered by Sub-Clause 8.5.
The 2017 edition provides more detail on certain delay issues, including exceptionally adverse climatic conditions and concurrent delays. It also clarifies aspects of the EOT entitlement and its relationship with the claims procedure.
Practical implication: Contractors should maintain an accepted baseline programme, regular updates, delay-event records, and a clear analysis of the effect on the critical path. An event causing delay does not automatically establish entitlement to an EOT; the contractual basis and actual effect on completion must be demonstrated.
C. Advance Warning and Programme Requirements
Both editions contain programme-related obligations. Under the 1999 edition, Sub-Clause 8.3 includes an advance-warning requirement. The 2017 edition separates advance warning into Sub-Clause 8.4 and provides more detailed programme requirements under Sub-Clause 8.3.
The purpose of advance warning is to identify events or circumstances that may adversely affect the works, increase the Contract Price, or delay execution, so the parties can consider appropriate action.
Practical implication: Contractors and project teams should raise foreseeable problems early, keep the programme updated, and document mitigation measures. Advance warning should not be treated as a substitute for a formal Notice of Claim where one is required.
D. Contractor’s and Employer’s Claims
One of the most important changes is the claims procedure.
Under the 1999 edition, Contractor’s Claims are generally dealt with under Sub-Clause 20.1, while Employer’s Claims are addressed under Sub-Clause 2.5.
Under the 2017 edition, both parties’ claims are dealt with under the common framework in Clause 20, particularly Sub-Clause 20.2. This creates a more structured procedure for claims made by either party.
The main timing differences include:
- Notice of Claim: The Contractor generally has 28 days under both editions.
- Fully detailed claim: The general period increases from 42 days in 1999 to 84 days in 2017.
- Late notice: The 2017 edition introduces a more detailed process for the Engineer to address a potentially late Notice of Claim.
- Supporting evidence: The 2017 edition sets out more explicit requirements for the content and supporting particulars of a fully detailed claim.
The 2017 process is not simply a longer deadline. The required notices, responses, records, and procedural steps must still be followed.
E. Dispute Resolution: DAB vs DAAB
Under the 1999 edition, the Dispute Adjudication Board (DAB) is addressed within Clause 20, which also covers claims and arbitration.
The 2017 edition separates claims from dispute resolution. Clause 20 addresses claims, while Clause 21 covers disputes and arbitration. The board is renamed the Dispute Avoidance/Adjudication Board (DAAB), reflecting its additional dispute-avoidance function.
Practical implication: Parties should consider referring emerging disagreements to the DAAB process in accordance with the contract, rather than allowing unresolved issues to accumulate until project completion.
4. Which Edition Is Better for Construction Projects?
The 2017 edition provides more detailed procedures and clearer steps for handling claims, programmes, and determinations. This can improve contract administration when the parties understand and follow the requirements.
However, the 1999 edition remains relevant to projects where it has been adopted contractually. A newer edition is not automatically applicable simply because it is more recent.
The appropriate choice depends on the project, the parties’ requirements, the governing law, the contract’s Particular Conditions, and the capability of the project team to administer the chosen form.
5. Practical Advice for Contractors and Contract Managers
When working with either edition:
- Confirm the exact edition and any amendments incorporated into the contract.
- Use the correct clause references for notices and claims.
- Track notice and submission deadlines.
- Maintain contemporary records and updated programmes.
- Demonstrate how delay events affect the critical path and completion date.
- Record Engineer consultations, agreements, and determinations.
- Monitor deadlines for Notices of Dissatisfaction and dispute referrals.
- Obtain professional advice where contractual entitlement or time-bar provisions are disputed.
Conclusion
The FIDIC Red Book 1999 and 2017 share the same broad purpose, but the 2017 edition introduces more detailed procedures for claims, programmes, the Engineer’s determinations, and dispute resolution.
The most significant changes include the move from Sub-Clause 20.1 to 20.2 for claims, the extension of the general period for a fully detailed claim from 42 to 84 days, the revised Engineer’s determination procedure, and the introduction of the DAAB.
For construction professionals, understanding these differences is essential for effective contract administration and reducing avoidable disputes. Always apply the wording of the actual contract, including its Particular Conditions and amendments, rather than relying solely on a general comparison.
Disclaimer: This article provides general educational information and is not legal advice. The contract wording, amendments, and applicable law determine the parties’ rights and obligations.