This is Part 2 of our three-part series on Extension of Time (EOT). Part 1 explained the meaning, importance and common grounds for EOT. In this part, we cover the relevant FIDIC provisions for EOT in the 1999 and 2017 Red Books.

4. Relevant FIDIC Provisions for Extension of Time

Watch: FIDIC Extension of Time Clauses Explained: 1999 vs 2017 Red Book

The FIDIC Conditions of Contract provide a structured mechanism for granting Extension of Time.

The relevant provisions differ between the FIDIC 1999 and 2017 editions.

A. FIDIC 1999 Red Book

Sub-Clause 8.4 – Extension of Time for Completion

Under Sub-Clause 8.4 of the FIDIC 1999 Red Book, the Contractor is entitled, subject to the contractual requirements, to an extension of the Time for Completion if completion is or will be delayed by specified circumstances.

The principal grounds include:

  • A Variation or other substantial change in the quantity of an item of work included in the Contract.
  • A cause of delay giving an entitlement to EOT under another Sub-Clause of the Conditions.
  • Exceptionally adverse climatic conditions.
  • Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or governmental actions.
  • Any delay, impediment, or prevention caused by or attributable to the Employer, the Employer’s Personnel, or the Employer’s other contractors on the Site.

The contractor must follow the notice and claims procedure under Sub-Clause 20.1.

Sub-Clause 20.1 – Contractor’s Claims

Sub-Clause 20.1 establishes the procedure for submitting claims, including claims for EOT.

The principal requirements are:

  • The contractor must give notice describing the event or circumstance giving rise to the claim as soon as practicable and, generally, no later than 28 days after becoming aware, or when it should have become aware, of the event.
  • The fully detailed claim is generally required within 42 days after the contractor became aware, or should have become aware, of the event or circumstance, unless another period is agreed or otherwise applicable under the contract.
  • Where the event has continuing effects, interim claims are submitted at monthly intervals, followed by a final claim within 28 days after the end of the effects, subject to the contract wording.

The Engineer then considers the claim and proceeds in accordance with the contractual determination procedure under Sub-Clause 3.5.

B. FIDIC 2017 Red Book

Sub-Clause 8.5 – Extension of Time for Completion

In the FIDIC 2017 Red Book, the corresponding provision is Sub-Clause 8.5, which deals with Extension of Time for Completion.

It provides for EOT where completion is or will be delayed by qualifying circumstances specified in the contract.

These include, broadly, variations, causes giving entitlement under other provisions, Unforeseeable adverse climatic conditions at the Site, unforeseeable shortages caused by epidemic or governmental actions, and delays attributable to the Employer or its personnel and other contractors.

The contractor must demonstrate that the relevant event has affected the Time for Completion and comply with the contractual claims procedure.

Sub-Clause 20.2 – Claims for Payment and/or Extension of Time

The 2017 edition provides a more detailed claims procedure under Sub-Clause 20.2.

Important requirements include:

  • Notice of Claim: The contractor must generally give notice within 28 days after becoming aware, or when it should have become aware, of the event or circumstance giving rise to the claim.
  • Initial response: Where the Engineer considers the Notice of Claim to be late, the Engineer must respond within 14 days; if no response is given within this period, the Notice of Claim is deemed valid, although the other Party may still dispute it.
  • Fully detailed claim: The contractor is generally required to submit a fully detailed claim within 84 days after becoming aware, or when it should have become aware, of the event or circumstance, subject to the contract’s provisions.
  • Continuing effects: Where the event has continuing effects, the contractor must submit interim claims at specified intervals and a final claim after the effects have ended.

The Engineer deals with the claim in accordance with the agreement and determination procedure under Sub-Clause 3.7.

Note: The above provisions describe the standard FIDIC forms at a general level. Particular Conditions, amendments, and project-specific contract requirements may modify these provisions. The signed contract must always be examined before determining entitlement.

Apart from Sub-Clause 8.4 in the 1999 edition and Sub-Clause 8.5 in the 2017 edition, several other provisions may be relevant to EOT claims.

FIDIC provisionSubjectRelevance to EOT
Sub-Clause 1.9 (1999/2017)Delayed Drawings or InstructionsMay provide entitlement where delayed drawings or instructions affect progress.
Sub-Clause 2.1 (1999/2017)Right of Access to the SiteRelevant where the employer fails to provide access as required.
Sub-Clause 4.12 (1999/2017)Unforeseeable Physical ConditionsDeals with qualifying unforeseen physical conditions encountered during execution.
Sub-Clause 8.3 (1999/2017)ProgrammeRelates to the submission and updating of the construction programme.
Sub-Clause 8.7 (1999) / 8.8 (2017)Delay DamagesDeals with delay damages for failure to complete within the applicable contractual period.
Sub-Clause 20.1 (1999) / 20.2 (2017)Contractor’s Claims / Claims for Payment and/or EOTPrescribes the claims procedure.

These provisions should be read together. A contractor may rely on a specific clause establishing the underlying entitlement and the applicable claims clause for the procedure to be followed.

Continue to Part 3: EOT Claims Explained – Assessment, Documents & Prolongation Cost, where we look at how an EOT claim is assessed and the documents required.

RP
Written byRajesh Pant

Rajesh Pant is a Civil Engineer and Infrastructure Management professional with approximately 25 years of experience in the planning, implementation, coordination, management and execution of large-scale government infrastructure projects. His professional experience encompasses project management, procurement, contract administration, construction management and quality control of infrastructure projects. He also possesses nearly eight years of experience in Externally Aided Projects (EAPs), particularly in project implementation, procurement and contract management of World Bank-funded projects. His professional exposure includes working with projects financed by multilateral development organisations, providing valuable insights into international procurement practices, project implementation frameworks and contract management requirements. He holds a Master of Technology (M.Tech.) in Civil Engineering and a Master of Business Administration (MBA) in Infrastructure Management, combining technical engineering expertise with management and administrative capabilities. With extensive experience in public infrastructure development and government project management, Rajesh brings a practical, multidisciplinary perspective to the fields of contract management, procurement, project management and construction management.

More from the author
Keep reading

Related articles

View all
Newsletter

Keep learning with every new post.

Subscribe so you do not miss any of our fresh posts from the management enthusiast.